Proyek pembangunan LRT Jakarta capai 63,01 persen

LRT Construction Project Reaches 63 Percent

PT. Jakarta Propertindo (Jakpro) Director, Satya Heragandhi informed, Light Rail Transit (LRT) project construction progress has reached 63.01 percent by February 15, 2018.

While another eight LRT cars will be prepared to operate by the end of July 2018

"Its work preparation has completed 100 percent, infrastructure main construction reaches 62.92 percent, facility rolling stock construction reaches 59.21 percent. Overall it reaches 63.01 percent," he explained, Thursday (2/22).

He added, facility construction has been started in December 2016 and targeted to complete in August 2018. While for testing and commissioning are targeted to start in early May 2018. Then for rolling stock procurement contract has been started on February 1, 2017 and targeted to complete in October 2018.

Governor is Optimistic to Complete Asian Games Infrastructures On Time

First train has painted in October 2017 in Korea. The first two train cars will be arrived in Jakarta at least in April 2018 and ready for testing and commissioning.

"While another eight LRT cars will be prepared to operate by the end of July 2018 and next eight LRT cars will be ready to operate by the end of October 2018," he conveyed.

Linked News
Popular News indeks
  1. Jakarta Endorses New Housing Project for Residents on Railway Embankments

    access_time28-03-2026 remove_red_eye2402 personDessy Suciati
  2. Pramono Affirms Commitment to Enhancing Regional Financial Management Quality

    access_time02-04-2026 remove_red_eye787 personTiyo Surya Sakti
  3. Pramono Calls for Enhanced Synergy at DPRD Post-Eid Gathering

    access_time30-03-2026 remove_red_eye695 personDessy Suciati
  4. Banners Prohibiting Illegal Parking Levies Installed at Blok M Square

    access_time02-04-2026 remove_red_eye634 personTiyo Surya Sakti
  5. Kampung Rambutan Terminal Sees Increase in Intercity Bus Passengers

    access_time03-04-2026 remove_red_eye469 personNurito